10-17-10

Jeff installed pressure-treated drip caps on top of most of the windows and window headers on the rear wall. Each cap is cut so that the top slopes to shed water. Each piece overhangs the front edge by about 1/2". Jeff also worked on the soffit paneling and the front door opening.

no additional pics for today

     
 

10-27-10

Jeff spent most of the day working on the front wall, installing drip caps and siliconing the windows. He also installed a few corbels under some twin double-hung windows that needed extra support. Bob was on the scaffolding working on the back wall, and Brendan stopped by and did some interior insulating.

no additional pics for today

     
 

10-28-10

It was more of the same today on this cloudy, windy day. Jeff installed more drip caps on the front windows, siliconed around them, and spray-foamed any small openings on the front wall. Bob continued on the back wall with the foam board and spray foam.

no additional pics for today

     
 

10-30-10

Jeff installed another set of drip caps and more corbel supports while Ted, Bob, and Mike worked on the back wall. In the evening, Jeff started on the insulation for the upper 2 feet of the basement wall.

no additional pics for today

     
 

10-31-10

This afternoon, Jeff installed more drip caps. It was a very gloomy day, threatening rain all afternoon, but the rain held off. After sunset, it was back to the basement to put up more wall insulation.

click here for more pics

     
Back to Fall 2010 Projects

BACK TO OUR LOG HOME PAGE


If you have any questions about this website, e-mail us at stargazer@stargazerpics.com.


These pages and their contents Copyright © All Rights Reserved.