4-3-09
 
 
John finished leveling the rest of the piles in the front yard, then moved to the west side to push a little more fill up against the basement insulation panels.
Bob in his yellow rain gear...
...and Jeff in his camo gear.
After all the work they did at undoing last week's work and re-leveling the corners, Bob and Jeff brought the last two wall logs over, trimmed off the knots, and cut them down to a length of 40 feet. These are the double-butt logs that will sit on the north and south walls between the double-pass logs. They'll get cut to exact length once their up on the wall and the other two are pinned in place.