Bob Caswell dug out a pit outside the daylight wall for a double frost wall. The forms were all assembled quickly in the morning.
 
Later in the morning, the forms arrived for the walls which should go up on Monday the 19th.
     
 
Forms for the double frost wall. A concrete patio slab will span here. The right wall will support the daylight wall in the basement. The left wall will support the back of the patio and future rear deck posts.
 
The concrete trucks arrived at 2:00 and pouring began. It took two truckloads to complete the frost walls and footers.
     
 
Smoothing off the top of the west footer.
 
Working on one of the footers for a log support column that will hold up a floor girder.
     
 
Pouring concrete into the second log support column footer.
 
A view of the completed northwest corner and west wall.
     
 
Beginning to pour the double frost wall on the back side of the house.
 
Filling the form for the rear frost wall for the patio.
     
 
The second truck had enough leftover concrete to pour behind the wing walls of the culvert pipe.
 
John (right) guides the chute to pour next to the pipe.
     
 
Adding a bit more concrete to the 4th wing wall.
 
A large train of curious visitors. (gobble gobble)
     
 
Finishing off the double frost walls.
 
The final task for today - setting the vertical rebar to tie into the future concrete walls.
<-- BACK TO CONSTRUCTION (PHASE 2) PAGE  

BACK TO OUR LOG HOME MAIN PAGE


If you have any questions about this website, e-mail us at stargazer@stargazerpics.com.


These pages and their contents Copyright © All Rights Reserved.